A practical buyer guide to verifying a pelletizer before it leaves the supplier.
Buying a dry ice pelletizer is not the same as accepting a working production system. A catalogue can describe capacity, pellet diameter and machine functions, but only a properly documented factory acceptance test (FAT) can show how the agreed unit behaves under specified test conditions. For overseas buyers, that distinction matters: correcting a mismatch before shipment is usually easier than discovering it after electrical and CO2 connections are installed.
At OLLITAL, we recommend treating FAT as an agreed evidence package rather than a brief demonstration video. The goal is to establish what was tested, what was measured, what passed, and what remains open for site commissioning. A dry ice production FAT should be specific to the purchased model, the chosen die, the available liquid CO2 supply and the downstream collection arrangement.
A useful FAT starts with the purchase contract. It should verify the as-built machine identity, the functions included in the order, the performance indicators the supplier and buyer agreed to witness, and the documentation that will accompany shipment. It does not prove how the machine will perform under every future site condition. The site acceptance test (SAT) still needs to verify local utilities, CO2 storage and connections, ventilation, operator training and downstream integration.
When we discuss a dry ice production machine with a buyer, we separate three types of evidence: visual and functional checks; measured performance; and commercial/documentary completeness. A smooth start-up alone is not a capacity test. One tray of attractive pellets is not evidence of stable output over an agreed period. A general factory photograph cannot prove the final machine configuration.
OLLITAL currently lists compact and industrial-capacity systems in its dry ice production machine range. Model pages provide useful selection references, but final acceptance criteria should come from the confirmed quotation and FAT protocol.
Before the test, the parties should identify the exact model and configuration. Record the equipment identifier, control-system version where applicable, die diameter(s), inlet and outlet arrangement, electrical specification, optional recovery components, and any agreed accessories. The buyer should be able to match this record to the machine shown during the test and to the packing list.
The test record must also describe the liquid CO2 supply conditions. Supply temperature, pressure, available liquid-phase feed and upstream stability can affect dry ice formation and collected output. Record how the input quantity is measured and whether a dedicated CO2 recovery system is connected. If the supplier cannot reproduce the contracted test conditions at the factory, identify the limitation in writing and decide whether to defer that part of acceptance to the installation site.
Define a measurement window in advance: when warm-up or start-up ends, when the timed production interval begins, how product is collected, which stoppages count and whether any product is lost during transfer. Agree on the scale, calibration/verification status and tare procedure. The same definition should be used for every run so that comparisons are meaningful.
For example, the public 250 kg/h dry ice pellet production machine page lists representative model information and an important note that published parameters are for reference and must be confirmed for the actual equipment. Those numbers should not be treated as automatic FAT pass limits.
The critical production metric is the mass of accepted pellets collected during an agreed interval. Observe the running machine, but calculate output from net product weight and actual elapsed production time. A production cycle counter, hydraulic movement rate or controller display is not a substitute for weighing output.
Measured output (kg/h) = net collected dry ice (kg) ÷ timed run duration (hours). For illustration only, collecting 112.5 kg over a 30-minute defined production window corresponds to 225 kg/h. This arithmetic example is not an OLLITAL test result and does not establish a warranty tolerance for any model.
Repeat the calculation when required by the contract. Preserve notes on start-up discard, pauses, discharge blockage, pellet spill, manual interventions and any timing exclusions. If collection containers are changed mid-run, keep one continuous timing record and sum their net weights. Where dry ice sublimation during measurement could materially affect the result, shorten transfer delays and document the collection method.
Pellet diameter is a purchasing requirement because it affects the intended downstream use. Small pellets may be selected for blasting media, while larger formats can serve different cooling, packing or handling needs. The exact supported sizes and the die-change scope must be checked against the purchased configuration, not inferred from a general product family.
During the test, collect samples at the beginning, middle and end of the stable run. Confirm the installed die, examine nominal diameter and approximate uniformity, and document obvious broken fragments or excessive fines according to an agreed sample method. A visually neat sample is useful, but appearance alone is not a quantified specification. If the contract contains a pellet-integrity or dimension acceptance rule, use that rule and a defined inspection technique.
Ask for photos of the selected die and pellet samples beside a scale or ruler, with a clear machine/project identifier in the same inspection sequence. If multiple pellet sizes were purchased, document a controlled changeover or explicitly identify which sizes were not tested at the factory. A statement such as “multiple dies available” should not silently become proof that every accessory was supplied and trialed.

Illustrative pellet-discharge scene. For FAT, weigh accepted pellets over a defined period; do not infer production capacity from photographs.
The cost of dry ice production depends partly on how much liquid carbon dioxide is consumed to make saleable solid dry ice. A meaningful FAT needs both sides of the mass balance. Liquid-to-solid conversion is not simply a controller setting: agree where the input is metered, how product mass is weighed, whether the upstream supply quantity includes purges, and which intervals are included.
Observed conversion (%) = net accepted dry ice output (kg) ÷ measured liquid CO2 input (kg) × 100. For example, 96 kg of accepted dry ice from a measured 240 kg liquid CO2 input equals 40%. These are illustrative arithmetic figures, not a measured efficiency for any OLLITAL machine.
Be precise when the project includes gaseous CO2 recovery. A factory pelletizer may discharge gas from the phase-change process, and a separate recovery installation can change the overall plant material balance. Do not describe “gas recovery,” “liquid CO2 conversion” and “net purchased CO2 consumption” as the same metric. Record recovery boundaries and metering points separately. If recovery equipment is outside the purchased FAT scope, do not claim that its overall effect has already been verified.
Run through the normal start, steady operation, orderly stop and restart sequence for the supplied controls. Confirm that indicated alarms, emergency stop and other specified protective functions behave as described in the machine documentation. Only qualified personnel should test protective functions, under a written safe test procedure. Never defeat a guard or interlock simply to keep the video running.
Inspect leakage indicators, abnormal vibration or noise, pressure behavior, discharge continuity and control warnings during the agreed observation period. A FAT should document the actual operating status of the tested machine, not claim “24-hour stable production” when a much shorter run was completed. Longer-duration testing is a contractual matter; record its duration and interruption rules before it begins.
Carbon dioxide is an asphyxiation hazard at elevated concentrations, and dry ice or liquid CO2 can cause cold injury. Testing therefore needs appropriate ventilation, site-specific CO2 monitoring and emergency arrangements, plus protective equipment and safe handling procedures. These controls should be reviewed by the responsible site team; a generic article or supplier video cannot certify that an installation is safe.
The most useful remote or in-person test is one that leaves a simple audit trail. The following matrix can be adapted into a buyer-supplier acceptance sheet. Acceptance limits and observation durations should be inserted from the contract, not filled in by assumption.
| Test item | Evidence to retain | Acceptance reference |
|---|---|---|
| Machine identity | Nameplate / identifier, as-built photos, component scope | Signed quotation and drawing |
| CO2 and utilities | Supply conditions, metering points, power configuration | Approved test plan |
| Run and output | Timed video, net weight log, interruptions, result calculation | Agreed output method and limits |
| Pellet specification | Die ID, samples, size/fines records | Purchased pellet size and criteria |
| CO2 balance | Input meter log, output mass and scope of recovery | Defined conversion calculation |
| Controls / safety | Startup, shutdown, alarms and safe-function witness log | Machine documentation / FAT script |
| Delivery package | Photos, manuals, spare-parts and packing records | Confirmed order scope |
Use the status fields “pass,” “open item” and “not tested,” with responsible person and target close-out date where needed. A test that was not performed is not necessarily a machine failure; it is a scope gap that the parties need to resolve explicitly. Do not approve shipment on the assumption that all missing evidence will be easy to reproduce later.
For an overseas buyer, remote witnessing can work well if the video sequence and records stay connected. Begin with the project reference and machine identification. Show the installed die and connections, then the agreed start-up and timed run. Keep the clock, collection steps and weighing method auditable. Record a separate close-up of the control panel and any alarm-response test, with no invented values superimposed on the video.
After the live demonstration, request a signed FAT summary, sample photographs, test logs, unresolved-item register and matching packing/document list. Where a load-dependent test cannot be carried out in the factory, document the reason and agree how it will be performed at site acceptance. This is more useful than accepting a polished, edited compilation without a clear time and product trace.
FAT approval should define whether the machine is accepted for shipment, accepted subject to named minor open items, or not accepted pending corrective action. That decision belongs in a written record. Important functional or safety issues should not be hidden in a general promise to correct matters during installation.
Match the final equipment photographs to the package list. Verify purchased dies, hoses, fittings, operating documents, electrical information, spare parts and any site-specific accessories. Confirm preservation, packaging and identification methods for export. Where the supply includes upstream CO2 components or downstream packaging/storage interfaces, ensure the machine-side connection information is in the final drawings.

Illustrative weighing and inspection scene. Net weight, tare, timing and sample identification should be recorded in the actual FAT log.
Which exact dry ice pelletizer model, die sizes and options will be delivered, and can you show a current as-built reference?
Under what liquid CO2 conditions will output and conversion be measured, and how will the input quantity be recorded?
What is the proposed timed production run, weighing method and acceptance criterion?
Which alarms, protective functions and start/stop sequences are included in the witnessed test?
Can our team attend remotely, and what uninterrupted test video, records and photos will we receive?
Which tests are factory-only, which are deferred to SAT, and how are unresolved items closed before shipment?
For broader supplier evaluation beyond the machine test itself, see our dry ice equipment supplier evaluation guide, which covers factory evidence, documentation, service and quotation scope.
A good dry ice pelletizer factory acceptance test does not need elaborate theatre. It needs the right machine, defined conditions, trustworthy mass measurements, representative pellet samples, observed controls and a written acceptance record. The critical habit is to agree on the method first and then interpret the results against the actual purchase contract.
At OLLITAL, we encourage buyers to share their hourly dry ice demand, preferred pellet diameter, expected liquid CO2 supply conditions and downstream storage plan early in the project. This helps us discuss an appropriate machine configuration and a test scope that is meaningful to the operation rather than just impressive on camera.