Dry Ice Cost per Kilogram: A Practical Buy-vs-Make ROI Worksheet

For industrial cleaning, cold-chain operations and dry ice distribution businesses

The right question is not “How much is the machine?”

When a customer asks us whether they should buy finished pellets or make dry ice on site, we start with one number: cost per usable kilogram at the point of use. The price on a delivery invoice is not necessarily the cost of dry ice that survives storage and reaches the cleaning station or packing operation. In-house production also has costs that do not appear on the pelletizer quotation.

At OLLITAL, our approach is to compare two complete supply routes under the same working conditions. If local deliveries are dependable and the plant uses dry ice only occasionally, buying finished dry ice may remain the simplest choice. If demand is frequent and predictable, a dry ice production machine may be worth evaluating—but only after checking liquid CO₂ availability, conversion yield, operating labor, storage and actual machine utilization.

This guide is a practical worksheet, not a promise of a particular savings rate. You can use it to assemble the costs that your team already knows, identify missing data and decide whether a formal equipment quotation is justified.

First, define what “usable dry ice” means for your plant

Start with the quantity consumed by the process, not the kilograms unloaded from a truck or discharged from a pelletizer. For a dry ice blasting operation, count the kilograms actually charged to the machine for a job or shift. For a distribution business, use the weight that meets the customer order at the agreed dispatch point. Those are different measurement boundaries, and the comparison must use one consistently.

• Daily demand and operating calendar. Record normal demand, peak demand, days per week and the number of working weeks per year.

• Supply-to-use delay. Note how many hours elapse between buying/producing dry ice and the moment it is used.

• Product specification. Confirm pellets versus blocks, diameter, acceptable fines and packaging requirements. A different product form can change both production feasibility and downstream handling.

• Handling and storage. Record storage-box type, opening frequency, transfers and any measured mass loss between supply and use.

For example, 300 kg of actual dry ice consumption per week over 48 operating weeks equals 14,400 kg of usable annual demand. That is only a demand example; it is not an expected operating figure for any particular plant.

Route A: the real cost of delivered dry ice

Buying dry ice is easy to describe but sometimes surprisingly difficult to cost correctly. We recommend keeping the purchase price, transportation charge and receiving loss separate. A single “price per kg” may hide delivery surcharges, minimum order quantities, returns or weekend service.

Delivered-supply input

Buyer measurement

Why it matters

Invoice price per kg

Local supplier quote

Start with the price for the required form and pack size

Delivery / handling fee

Cost per delivery or kg

Express orders and remote sites can be materially different

Purchased kilograms

Receiving weight

Compare with usable kilograms, not only invoiced quantity

Loss before use

Measured kg or %

Includes handling and sublimation during the chosen interval

Reliability exposure

Delayed shifts / backup stock

A low purchase price is less useful if supply is unpredictable

Delivered cost per usable kg = (purchase invoice + relevant delivery / handling charges) ÷ kilograms actually available at your chosen use point. If your supplier bills for a purchased quantity rather than measured receiving weight, keep that distinction visible. We would rather see one month of honest records than an attractive but untested percentage.

Route B: the real cost of producing dry ice on site

A pelletizer converts liquid CO₂ into solid dry ice through expansion, formation of CO₂ snow and compression. That process does not convert every kilogram of liquid CO₂ into saleable finished dry ice. The measured liquid-to-solid yield is therefore a key input, alongside power, staffing, maintenance, downtime and storage after production.

For equipment discussions we first ask how many kilograms the plant must produce within its actual available hours. A nominal output rate in kg/h should be treated as a capacity reference under stated conditions, not a guarantee of annual output or return on investment. The exact setup and test conditions need to match the quotation.

Dry ice pellet production equipment with cabinet controls and discharge outlet

What to confirm in a pelletizer configuration

At OLLITAL, we confirm the actual dry ice pellet production machine model, output rating, electrical supply, pellet die and liquid CO₂ requirements before a final quote. The cabinet, controls and discharge arrangement should be checked against the selected configuration.

Dry ice pellet production equipment with cabinet controls and curved discharge outlet; configuration varies by model.

The site work is just as important as the equipment. A complete budget may involve liquid CO₂ storage and deliveries, properly engineered piping, electrical installation, CO₂ ventilation and monitoring, operator training, spare parts and downstream handling. A claimed raw-material advantage disappears quickly if the plant ignores those operating responsibilities.

On-site production input

How to establish it

Common mistake

Liquid CO₂ cost per kg

Supplier quotation delivered to the site

Comparing finished dry ice with CO₂ commodity cost alone

Solid output yield

Machine trial under agreed conditions

Using nominal kg/h output as liquid CO₂ conversion

Electrical energy

Measured kWh for the actual production window

Counting motor nameplate kW as total kWh/kg

Operating labor

Paid time: startup, production, cleaning, documentation

Assuming every hour runs unattended

Maintenance and wear

Parts and service budget per year or kg

Omitting predictable service activities

Post-production loss

Difference between discharged and usable dry ice

Assuming new dry ice has zero sublimation loss

Setup and ownership

Tank, piping, safety, spares and equipment cost

Treating the pelletizer alone as the full project

The worksheet: compare like with like

We advise buyers to use a single annualized demand and to calculate both routes around that demand. Fill in each line with your company’s values. If a figure is not known, mark it “test required” rather than guessing. The cost of liquid CO₂ per kilogram of finished product is especially sensitive to real conversion yield.

Calculation line

Bought dry ice

Produced on site

Usable annual demand, kg

D = ______ kg

D = ______ kg

Material / invoice spending

Invoice total = ______

Liquid CO₂ cost = ______

Delivery / handling

Freight + fees = ______

CO₂ delivery / handling = ______

Power + labor + maintenance

Usually embedded or site-specific

Electricity + wages + parts = ______

Loss between supply and use

Measured loss = ______ kg

Measured loss = ______ kg

Annual cash cost

Total = ______

Total = ______

Cash cost per usable kg

Annual total ÷ D

Annual total ÷ D

Useful equations: Liquid CO₂ required (kg) = finished dry ice output (kg) ÷ measured solid yield (decimal). Annual cash savings = delivered-supply annual cost − on-site annual cash cost, after normalizing to the same usable output. Simple payback period = eligible upfront project investment ÷ positive annual cash savings.

Do not count the full equipment investment as an annual operating expense and then subtract it again through a payback calculation. For a lifetime ownership analysis, annualized capital or depreciation can be included with a clearly separate methodology; for simple cash payback, keep initial project spend separate from recurring cash costs. Finance, taxes, resale value and the time value of money may justify a more detailed financial model.

Utilization changes the economics more than a brochure suggests

Imagine two factories with the same nominal dry ice demand. One uses dry ice in short, unpredictable maintenance bursts; the other consumes it every weekday across predictable shifts. The second factory may be able to plan production nearer to use, spread operating tasks across more output and keep a smaller short-term buffer. The first may spend too much time starting, stopping and maintaining a production system for very little annual volume.

This is why we ask for the production window, not simply the daily tonnage. A larger machine is not automatically a faster payback. We would rather recommend an operating schedule that the customer can sustain than oversell output that stays unused for much of the week.

In the OLLITAL dry ice production machine range, buyers can review nominal output classes ranging from smaller pelletizers to large industrial configurations. For example, 50 kg/h, 250 kg/h and 500 kg/h equipment pages provide practical starting points for a model-specific engineering discussion. The final selection should follow verified demand, utilities and equipment configuration, not an assumed ROI from a capacity label.

Do not let storage quietly erase the savings

Whether you buy pellets or produce them, dry ice changes directly from solid to CO₂ gas over time. Shorter waiting periods and good handling may help protect usable output, but even a well-insulated box does not stop sublimation. For fair costing, we compare both supply methods at the same physical handoff point.

Insulated dry ice storage box used as a short-term production buffer

Storage is a working buffer, not a cost-free warehouse

An insulated dry ice storage box supports temporary holding and movement between production, packing and use. We recommend measuring handling frequency and sublimation loss. Gray boxes with yellow lids are one available format; the required capacity depends on the actual workflow.

Short-term dry ice storage must reduce heat gain while allowing CO₂ gas to vent safely.

The operational rule is straightforward: size the buffer around real replenishment and use, open the container only as needed, and keep appropriate ventilation and CO₂ risk controls. Dry ice must never be stored in a rigid, pressure-tight arrangement that can trap expanding gas. We also ask buyers to review insulated box options in the same equipment conversation, rather than pricing production with no thought for the first hour after discharge.

Three purchasing scenarios we discuss with customers

1. Occasional cleaning with reliable local delivery

If dry ice blasting is scheduled once or twice a month and a local supplier can deliver a suitable pellet size close to the cleaning time, delivered dry ice may remain the sensible solution. Avoid buying a separate production line simply to eliminate a relatively small annual purchase bill. Improve delivery timing, packaging and short-term handling first.

2. Repeated weekly demand at one facility

If a plant uses dry ice on many working days, an in-house machine becomes a realistic option. We would ask for several weeks of usage records, a quote for liquid CO₂, the usable production window and a realistic plan for operators and maintenance. A test run can then establish the actual output, yield and media quality used in the financial model.

3. Multiple users, delivery routes or peak-demand periods

Where dry ice serves several cleaning teams or customer orders, production planning and packaging may be as important as the machine itself. A small nameplate capacity can struggle with a short dispatch window, while a very large machine may be uneconomic outside seasonal peaks. We normally evaluate daily order concentration, buffer storage and contingency supply before discussing expansion.

Seven questions to settle before requesting a quote

• What is our verified usable demand per week and per year, including a realistic peak?

• What does our supplier charge for delivered dry ice at the actual order size and delivery frequency?

• Is suitable liquid CO₂ reliably available, and what does it cost delivered to the site?

• What yield, pellet size, energy use and operating window can be demonstrated for the exact quoted machine?

• What site provisions are needed for tank, piping, electricity, ventilation, gas detection and safe handling?

• What happens during maintenance, weekends, supplier disruption or unexpected peak demand?

• What do we intend to measure before making the final buy-versus-make decision?

For projects involving a larger tank or multiple shifts, we also recommend checking our liquid CO₂ storage tank selection guide. The upstream CO₂ supply must be designed together with the selected production equipment; it cannot be treated as an unrelated purchasing line.

Frequently asked questions

Is making dry ice always cheaper than buying it?

No. The answer depends on liquid CO₂ cost, actual yield, utility and labor costs, machine utilization and loss before use. For occasional users, buying finished dry ice can be less complicated and less expensive overall.

Why should the calculation use usable kilograms?

Dry ice can lose mass while being delivered, held or handled. Comparing invoiced delivered weight with machine discharge weight would misstate the economics if the two supply routes have different holding times.

Can I calculate liquid CO₂ consumption from machine output?

You need the actual liquid-to-solid conversion result for the specified setup. Divide finished dry ice kilograms by the measured yield in decimal form and confirm whether the test boundary includes any recovery arrangement.

Should we choose the highest kg/h machine we can afford?

Not necessarily. Check how much product is needed during the real production window. Oversizing can leave equipment underused, while undersizing may require long shifts or too much buffer inventory.

Does an insulated storage box eliminate dry ice loss?

No. It reduces unwanted heat gain but does not stop sublimation. Appropriate CO₂ venting and ventilation remain essential.

What documents help OLLITAL prepare a useful proposal?

Share consumption history, dry ice form and size, schedule, available liquid CO₂ supply, power, floor space, downstream packing or storage needs and the intended acceptance criteria.

A purchasing decision grounded in your own numbers

At OLLITAL, we do not believe every customer needs a dry ice production machine. The strongest projects are those where the operating demand, material supply and economics support one another. A buyer who starts with measured usage and an honest cost boundary is much more likely to choose the right system than one who starts with a promising headline capacity.

If you already know your current dry ice purchasing volume, delivery price and working schedule, we can use those figures to discuss suitable production options and what needs to be validated in a trial. Explore our dry ice production equipment or contact OLLITAL with your project requirements. We will focus the conversation on the complete supply solution, not just the machine model.